November 18, 2025

New leak detection technology saves Hailey 59M gallons of water annually

New leak detection technology saves Hailey 59M gallons of water annually

Leak detection technology reveals 22 previously undetected leaks

The City of Hailey, Idaho, deployed a new AI-driven leak detection technology on 62 miles of its water distribution network and found 22 previously undetected leaks that were losing a total of 59 million gallons of clean water every year. 

 

The challenge:

The City of Hailey is a small city situated in Idaho’s Wood River Valley, with a population of a little over 9,900 people. Though both the Big Wood and Little Wood rivers run through the region, Hailey’s water distribution network was in need of attention.

Between 2019 and 2023 the city estimated that some 29% of the water that it was producing was not reaching consumers. This unaccounted-for water, or non-revenue water (NRW), reached 50% during the winter months.

The city identified three possible causes of this NRW:

  • Leaks in distribution system pipes
  • Faulty or inaccurate water meters
  • Unmetered connections

The problem with leaking water pipes, however, is that they are invisible, and therefore difficult to locate—or even detect—with any degree of confidence using traditional detection methods.

To address this, city leaders solicited assistance from specialized leak detection companies.

 

The solution: CivilSense™ real-time leak detection technology

Solution selection

City leaders asked Eric Landsberg, PE of Clear Solutions Engineering to evaluate leak detection technologies and services from three different providers: Echologics, Asterra, and Oldcastle Infrastructure.

Echologics offered leak detection technology that the city’s workers would install and operate. Relying on existing city resources to undertake both deployment and analysis was considered unviable as the city’s workforce was already stretched thin.

Asterra offered analysis of satellite imagery, using data over a range of wavelengths to identify areas where soils were saturated, suggested the possible presence of a leak. However, local geography is characterized by rocky terrain that does not retain water, meaning that this technique would be unsuited to the requirement.

Mr Landsberg instead recommended that the city use Oldcastle Infrastructure’s CivilSense™ solution, an AI-driven risk analysis and real-time leak detection technology that uses acoustic sensors and an AI trained on over 2.3 million acoustic signatures to detect, locate and size leaks in the water distribution network.

Landsberg recommended the CivilSense™ approach because of its “turnkey” nature, in which the CivilSense™ team would deploy sensors and the AI would conduct the analysis, as it avoided adding to the resource burden on the city’s workforce. He also noted the fact that its >93% accuracy meant that it delivered superior leak detection than either competitor.

The project

Oldcastle Infrastructure deployed CivilSense™ on a 62-mile section of the water distribution network, including mains, service lines and related infrastructure.

CivilSense™ field experts deployed acoustic sensors across the targeted section of the network, and created a total of 807 investigation sessions. These investigation sessions gathered acoustic data that was fed into the CivilSense™ AI for analysis.

The AI, powered by FIDO Tech, performed comparative analysis using its curated library of more than 2.3 million acoustic signatures to generate 220 Waypoints that indicate potential leaks in the system.

What is a Waypoint?

A Waypoint is an acoustic signature that the AI has assessed to be consistent with a leak based on comparison against a comprehensive library of previously detected and validated acoustic signatures. Waypoints are validated and pinpointed using sensors and a technique called correlation, which confirms and then precisely determines the location of the leak.

The field teams used the results of this analysis to redeploy sensors upstream and downstream of each of the Waypoints, and—using cloud computing and a technique known as correlation—this additional acoustic data enabled the AI to eliminate Waypoints that were not leaks, and to validate, locate and size the Waypoints that were leaks. The leaks were then marked up in situ to direct the resulting repair activity.

 

The outcome

The CivilSense™ team created 880 investigation sessions, from which the AI generated 220 Waypoints. Of these Waypoints, CivilSense™ analysis identified 22 previously undetected leaks in the targeted section of network, and pinpointed their locations for repair crews.

The leaks were discovered across a range of network infrastructure assets, including main lines, service lines and fire hydrants. Of these, seven were assessed as large leaks, six as medium and four as small. In addition, CivilSense™ was able to pinpoint the location and assess the sizes of five leaks that were known about but which could not be located.

In total, applying AWWA nominal volumetric values, the leaks were assessed to be losing a combined volume of around 59.2M gallons of water every year.

By revealing this loss and enabling the City of Hailey to conduct targeted repairs to address the leaks, CivilSense™ leak detection technology is helping the city address its leaks, improve system efficiency and make budgetary savings that can be reinvested into the community.

 

Learn more

November 6, 2025

Washington DC Substation

Washington DC Substation

The Situation

A leading energy provider that services customers in Maryland and the District of Columbia approached Oldcastle Infrastructure for a solution to repair a set of critical substations. Federal agencies require utilities to identify key substations essential to the performance of the power grid. There are approximately 55,000 substations nationwide, many in extreme disrepair. In this case, the concrete trenches housing multiple cable platforms in the substations were breaking down and cracking. If this critical substation were to power down, it could have disastrous implications for the electrical grid.

 

The Challenge

Trenches physically protect communication cables that control the devices that automate the grid. Replacing these trench systems in the substations safely and without taking an outage presented significant obstacles. Especially when considering that the critical power surrounding Washington DC is 500 kV.

To repair these trenches, the contractor would typically remove the trench and in the process disturb the cables. Additionally, rebuilding the trenches without disturbing the cables was simply not feasible.

Any disturbance or break of the existing cables could cause an outage in the substation. Also, during the problem-solving stage of the project, we were presented with another unique situation: the site’s physical position restricted the ability to use mechanical means inside the substation.

The repair work also had to be accomplished with the substation operating hot. If an outage were to occur, all cabling would have to be exposed, dug up and rerouted, which would take up to a year or more to remedy. This would again mean the loss of power to critical areas.

 

The Solution

The first two traditional solutions presented, namely cast-in-place and precast cement, were rejected, with cast-in-place immediately judged as being unviable due to the site limitations on heavy mechanical equipment.

The Oldcastle Infrastructure team approached the drawing board on this highly challenging project with a collaborative, problem-solving framework. Through customer-centric ideation and an innovative mindset, we arrived at an out-of-the-box solution.

We found a solution to reconfigure a STAKKAbox Ultima Connect product. Normally used to make highly effective manhole vaults, individual pieces of the modular STAKKAbox Ultima Connect system were repurposed to make a trench that was high strength while also being lightweight and flexible.

The team demonstrated the STAKKAbox Ultima Connect and installed a pilot section to determine if the product would work. Although skeptical at first, the construction team realized the value of the Ultima Connect system and the speed of installation. More importantly, the key requirement of not touching or moving communications cables would be met.

Additional enhancements included:

  • Supplying orange Plastibeton custom covers to give a clear visible signal of pedestrian rating.
  • Redesigning support beams to reduce weight and allow for greater interior room.
  • Designing supports to ease installation and increase lateral support on the structure.

 

The Outcome

Safer substation
As safety hazards were eliminated, crews can now walk safely around the substation. All cable is encapsulated and extremely well protected by the STAKKAbox Ultima Connect system. Safety orange Plastibeton custom covers are now much easier to notice to prevent vehicular traffic.

Better protected grid
Our protective Plastibeton custom covers are built to last. They will not decay or break down over time.

Zero maintenance
Yes, zero maintenance requirements for years to come. The customer really appreciates that.

Trusted partnership
The customer asked, “Can you fix my problem?” In close consultation with customer and contractor, the team found the best solution for this challenging scenario.

Customized solution
The flexibility of STAKKAbox Ultima Connect system allowed for the development of this clearly lighter, non-conductive product that can be assembled quickly, lifted safely by hand and fits perfectly into tight, complex configurations.

Blueprint for success
There are some two-dozen more substations in the region waiting for this customized fix, some with up to 10,000 feet of trench in substations measuring two miles long.

Robust connections
The ability to reach out across the network of CRH companies and innovate together is key to Oldcastle Infrastructure’s operational success. It’s all about finding the right solution for the customers’ needs.

Ultimately, the team created an innovative system to replace the existing trench, while allowing for future expansion. The customer was convinced the solution worked once the concept was proven on site.

 

Download this Case Study

Box culverts enhance ecosystem resilience for PA bridge replacement

Box culverts enhance ecosystem resilience for PA bridge replacement

The Situation

Located in Northeastern Pennsylvania’s Lackawanna County, Elmhurst Township is a small community intersected by State Route 435, a key connector to I-84 and the nearby towns of Scranton and Moscow.

Along its path, SR 435 crosses the heavily used Delaware Lackawanna Railroad and a tributary of Roaring Brook before passing over Roaring Brook itself – designated as a Class A Wild Trout Water feeding into the Lackawanna River.

The existing structures—a monolithic concrete and plate girder railroad bridge and a reinforced concrete arch—were assessed by the Pennsylvania Department of Transportation (PennDOT) as structurally deficient due to signs of significant deterioration. As a result, replacement was necessary to maintain the safety and reliability of the infrastructure for the traveling public.

 

The Challenge

As part of the SR 435 bridge replacements, additional improvements were required along Front Street and within the existing railroad drainage system to safely relocate traffic to a temporary roadway during construction.

Relocating traffic created new demands on this section of roadway, requiring upgrades to handle increased traffic volume. This included replacing the worn concrete pipes under Front Street and two aging box culverts beneath the railroad.

This reconstruction effort presented several challenges, including working adjacent to an active railroad, protecting a sensitive local river tributary, and operating within tight site constraints and difficult terrain.

 

The Solution

As part of the design strategy, PennDOT specified the use of precast concrete box culverts to preserve the natural flow of the tributary feeding into Roaring Brook, while minimizing environmental disruption. Precast culverts were selected for their proven durability, structural integrity, and efficiency in installation—qualities that support design lifespans exceeding 100 years.

To further align with environmental objectives, the culverts were designed with integrated baffles, allowing for the placement of natural streambed material within the structure. This feature helps maintain aquatic habitat continuity and supports the ecological health of the waterway.

PennDOT engaged Susquehanna Valley Construction Corporation (SVCC) to execute the construction phase of the project. SVCC selected Oldcastle Infrastructure as the preferred precast supplier, with all components manufactured at Oldcastle’s Telford, Pennsylvania facility, located just north of Philadelphia.

“As the contractor, it was critical that the culvert sections and hardware were delivered on time, in the requested sequence, and that all sections fit together seamlessly. Oldcastle Infrastructure’s shop drawings were precise and accounted for the tight field conditions between the staged box culvert installation and the railroad relocation.

Oldcastle Infrastructure not only delivered a high-quality product that met the project’s needs but also provided an experienced technician to properly install the post-tensioning elements on the day of assembly.

Oldcastle Infrastructure’s quality products and knowledgeable support enabled SVCC to successfully complete all contractual requirements for Front Street and the staged railroad box culverts.”

– Atlee Eshleman, Engineer, Susquehanna Valley Construction Corporation

The Outcome:

The project required two precast concrete box culverts to complete this initial phase of improvements:

  • Culvert 1: 7’ x 14’ opening, 38’ long and was used to replace the aging concrete pipes beneath Front Street.
  • Culvert 2: 7’ x 14’ opening – with a slightly thicker roof to accommodate railroad loading – 90’ long and was used to replace the deteriorated culverts under the railroad.

Installation of the second culvert was completed in two stages, coordinated closely with the railroad relocation to ensure uninterrupted rail operations.

This streamlined precast box culvert solution highlights the strength, durability, and precision of Oldcastle Infrastructure’s modern concrete systems.

Beyond improving the structural integrity—and therefore the safety—of the local transportation network, these new culverts also provided environmental benefits by maintaining and protecting the local aquatic ecosystem.

“The first priority for any project should always be safety, but projects like this remind us that if we select the right solution, we can deliver a range of benefits. Our box culverts not only provide a safe, solid base to upgrade local transport infrastructure but also serve to protect and maintain part of the local ecosystem.”

– Emily Schneider, VP of EHS & Sustainability, Oldcastle Infrastructure

 

Learn more

November 4, 2025

Wastewater reclamation plant retrofit improves performance and increases capacity

Wastewater reclamation plant retrofit improves performance and increases capacity

Retrofitting a HeadCell®, SlurryCup™ and Grit Snail® grit removal, washing and dewatering system provided a significant performance improvement over Fox Lake’s aerated grit basin.

 

The Problem

The existing aerated grit basin (AGB) grit removal system at Fox Lake Wastewater Reclamation Facility in Illinois was at the end of its useful life and needed to be replaced.

Plant operators had two requirements for the replacement: they wanted to retrofit the new equipment in the existing area and to eliminate grit deposition in the grit basin, which was very difficult, time-consuming and costly to remove.

Fox Lake’s Plant Supervisor Steve Vella saw the HeadCell® at WEFTEC in Chicago. He liked the stacked tray concept developed by Hydro International’s grit management experts and thought it would be the ideal solution to their plant’s grit problem.

The stacked tray design would allow them to significantly increase their treatment surface area, which would increase their grit system performance while staying within the existing area used by the AGB.

 

The Solution

To get the performance required to prevent grit from depositing within the plant, plant operators needed to double the surface area for settling grit. The stacked tray design of the HeadCell® allowed them to significantly increase their surface area while staying within their existing footprint.

An isolation wall was poured to section off a portion of the old aeration basin, making a dry pit for the grit pumps. The rest of the basin was used to house the HeadCell®. A SlurryCup™ and Grit Snail® replaced the old cyclone / screw washing and dewatering system to provide a complete Advanced Grit Management® system.

 

Testing

Prior to taking the AGB out of service, a grit study was performed on it. At the design peak flow, the aerated grit basin should have been removing 225-micron grit. At lower flows, the AGB should have performed even better; unfortunately, it did not.

Testing was performed during low flow conditions of only 824 gpm (52 L/s) when the aerated grit basin should have been removing all sand particles 75 micron and larger.

The data revealed that the separator was only capturing 58% of the incoming grit. To make matters worse, the cyclone / screw washing and dewatering system was retaining just 17% of the material delivered to it. This further reduced the overall system efficiency to only capturing 10% of influent grit.

 

The Outcome

Testing on a day with flows of 10 Mgal/d (38 MLD) proved the HeadCell® system to be 88% efficient overall.

The HeadCell® grit collection chamber alone reached 95% efficiency, while the SlurryCup™ and Grit Snail® washing and dewatering system successfully retained 93% of the grit it received. This represents a substantial performance improvement over the previous AGB system.

The new grit system significantly reduced the volume of grit that was passing through the old AGB and entering downstream treatment processes. The HeadCell ®-based Advanced Grit Management® setup minimized clogging issues, addressing the long-standing challenge of difficult grit removal.

As a result, the frequency of cleanouts was reduced, leading to lower maintenance costs, decreased labor demands, and improved operational reliability.

 

Upgrading for the future

Five years after installing the new grit removal system, Fox Lake installed a second HeadCell®, SlurryCup™, and Grit Snail® system to treat peak flows that exceeded the 25 Mgal/d (95 MLD) capacity of the original system.

The second system treats up to 12.5 Mgal/d (47 MLD) and is used in conjunction with the original HeadCell® system to treat the peak wet weather flows.

Together, the systems ensure Fox Lake’s wastewater reclamation plant remains resilient and efficient, even during peak wet weather events, demonstrating a long-term commitment to operational excellence, sustainability, and environmental stewardship.

 

Learn more

October 29, 2025

Precast concrete box culverts enable fish passage for bridge replacement

Precast concrete box culverts enable fish passage for bridge replacement

Precast concrete box culvert bridge replacement

Precast concrete box culverts replaced an aging bridge in Putnam, CT, preventing erosion and preserving fish passage in the brook that flows beneath.

 

The situation: aging infrastructure

Danco Road is a small road on the outskirts of Putnam, Connecticut that connects Park Road—and by extension I-395—with several local small businesses.

The road crosses Perry Brook, and the bridge over this small tributary of the Quinebaug River was determined to be in dire need of repair. The bridge culvert, originally made with corrugated metal pipe, had corroded away, and the bed of the brook was suffering from erosion.

Putnam Mayor Barney Seney told local radio station WINY that the town’s bridge inspection program had identified the bridge on Danco Road as being in poor condition:

“So, in the last eight years we’ve had a program to address this issue, and the Danco Road bridge was one of the bridges that, when it was inspected, it was determined that it was ready to fail.”

The town decided that the bridge needed to be replaced.

 

The challenge: disruption, erosion and fish passage

While the bridge is small—under 20 ft long—its replacement nonetheless presented challenges.

In the first instance, the roadway could not be closed down completely as it was the only route leading to and from the businesses and local residents.

In addition, the bridge needed to enable Perry Brook to flow freely beneath it, preventing erosion beneath the road and allowing fish to continue to pass.

 

The solution: precast concrete box culverts

The town made $1.6M available for the bridge replacement project—half funded from Putnam’s capital improvement funds, and half funded by grants from the State of Connecticut—and specified that the bridge be replaced by a series of four-sided precast concrete box culverts.

The town engaged general contractor NJR Construction of Thomaston, CT to carry out the work, and NJR Construction identified Oldcastle Infrastructure’s precast concrete box culverts as the preferred solution.

Supplied by the nearby Avon, CT plant, the box culverts are strong, versatile and extremely durable, providing corrosion resistance and design lifetimes of over 100 years.

“The placement of the new precast concrete box culvert bridge was the critical component of the project and needed to be fabricated and ready to be delivered to the project to meet our very aggressive schedule,” said Nicholas Mancini Jr, President of NJR Construction. “Tony Letizio of Oldcastle Infrastructure was instrumental in making sure the precast was properly fabricated and ready for delivery as our schedule required. Mr. Letizio maintained contact with our office and field personal throughout the entire process, allowing us to perform the work required for stage 1 of the project ahead of schedule.”

 

The outcome: safe infrastructure and environmental preservation

Although the project was delayed several times due to flooding caused by intense summer storms, the bridge replacement was carried out successfully and the new bridge is now in place.

The bases of the precast concrete box culverts were lined with small stones to prevent erosion and to provide a naturalistic riverbed to support the aquatic environment of Perry Brook, and the Connecticut Department of Energy & Environmental Protection (DEEP) has expressed satisfaction with its implementation.

Aging infrastructure is an acute issue across the US, and the Danco Road bridge is a perfect example of how even the smallest structures are in need of attention. With the 100+ year lifetime of precast concrete, however, this small bridge replacement project will have a lasting impact on the environment that surrounds it.

“Precast concrete is not often thought of as an environmental solution, but it all comes down to how it’s used,” said Emily Schneider, VP of Sustainability at Oldcastle Infrastructure. “By providing a stable, durable base on which a natural substrate can take hold, the box culvert preserves the character of Perry Brook and enables fish passage as though it were a natural environment, and its corrosion resistance and reliably long lifetime mean that this brook will remain in good condition for many decades to come.”

Learn more

October 22, 2025

Testing the Waters

Testing the Waters

How Collaborative Field Monitoring in North Carolina is Shaping the Future of Stormwater Technology

As towns and municipalities across the country become more developed, forests and meadows are being replaced by pavement and buildings. When it rains, stormwater runs off roofs and parking lots into the street, picking up everything from fertilizer, pesticides, bacteria and other pollutants. The untreated run-off then makes its way through storm drains and ditches to our rivers, lakes and oceans.

There’s no getting around it: polluted runoff is one of the greatest threats to clean water in the US. And without clean water, our world would be unrecognizable.

Fortunately, there are studies in the field that are helping to do something about it. Download the white paper to find out more.

June 27, 2025

Proactive city leaders use AI to cut water costs

Proactive city leaders use AI to cut water costs

Cutting the cost of water loss

Bartow County Water officials turned to AI-driven leak detection to identify, pinpoint and fix leaks in their water distribution network—helping them cut their annual water costs by $130,000. 

 

The challenge: out of sight, not out of mind

Bartow County Water supplies around 7.5 million gallons of water every day to its 108,000 residents in northwest Georgia, and as the utility acquires over 95% of its water from five external water systems it is strategically imperative that the water is used efficiently and cost-effectively. 

The city’s drinking water distribution network is large and complex, with around 24,000 connections spread across 900 miles of pipes of varying materials and diameters, and like many networks in the US, it suffers from water loss due to leakage. 

Officials knew that the network was losing water to leaks, but as water pipes are buried underground it was unable to detect and locate the leaks that were causing this non-revenue water loss. Resources were being used to fix large leaks and main breaks instead of driving efficiency by proactively preventing them. City leaders decided that they needed to take action. 

“We were mostly fixing leaks instead of finding them, and that was a costly way to address an ongoing problem. We were at the point where our leaks were so bad we just had to fix them without proactively trying to predict and find potential leaks. It was past time to see what we were actually dealing with here.” 

Lamont Kiser, Director of Bartow County Water

The solution: CivilSense™ AI-driven leak detection 

City officials identified CivilSense™ real-time leak detection as the solution that could make their invisible network visible, and they partnered with Oldcastle Infrastructure to address a high-priority area of the network. 

Bartow County Water identified an 80-mile section of the water distribution network that they considered to be at elevated risk of leaks, and the Oldcastle team designed a leak detection project that would provide detailed, specific insight into leak conditions.

Oldcastle experts strategically deployed highly sensitive acoustic sensors at almost 800 different points across the network, gathering detailed acoustic data that was fed into a proprietary AI. 

The AI, powered by FIDO Tech, analyzed the data and used comparative analysis against its curated library of more than 2.3 million acoustic signatures to detect, locate and assess the size of each leak. 

Using this analysis, field teams then redeployed sensors upstream and downstream of each of the identified leak locations and used cloud computing to pinpoint the location of each leak via a technique known as correlation. 

 

The outcome: reduced water cost

CivilSense™ detected nine previously unknown leaks in the section of network, including four large leaks that were discharging up to 20 gallons per minute and which represented a high risk of becoming a costly and disruptive main break. 

The leaks were discovered across a range of network infrastructure assets, including service lines, mains and hydrants. 

In total, CivilSense™ discovered leaks that were losing a combined volume of 83 gallons per minute, which equates to around 43M gallons of water every year. 

By addressing these leaks, Bartow County Water achieved a 17% reduction in non-revenue water that translates to a saving of $130,000 in variable production cost every year. Given the city’s reliance on external water sources, this reduced water cost and increased water distribution efficiency improves not only its sustainability and water resilience, but also its finances. 

The city has subsequently agreed a three-year follow-on partnership for CivilSense™ to analyze additional sections of the network to drive further water cost efficiencies. 

 

Learn more

MaxWell® helps LA County recharge groundwater 

MaxWell® helps LA County recharge groundwater 

Los Angeles County is reaping groundwater recharge benefits from its network of deep infiltration drywells. 

 

Situation

With a population of over 9 million people, Los Angeles County is the most populous county in the US, and its county seat, Los Angeles, is the second most populous city in the US after New York. 

Covering some 4,000 square miles, the county has a complex geography that encompasses urban, mountain and desert landscapes, and includes coastal zones, rivers and forest. 

In recent decades Southern California has been experiencing regular periodic droughts, and in combination with population growth and increasing agricultural and industrial demand, this has placed great pressure on supplies of fresh water. Some 30-40% of water used in the County is pumped from groundwater supplies as a local alternative to imported water. 

In recognition of this, Strategy 9B of the County’s 12 OurCounty sustainability initiatives is focused on improved water conservation, more efficient water usage, and better all-round water stewardship. Its actions include implementing a net zero water approach for new developments, and building code changes that improve water efficiency and usage. 

Further emphasizing its importance to the state, in January 2025 California Governor Gavin Newsom issued an executive order to direct local and regional agencies to maximize groundwater recharge through facilitating the diversion and storage of excess precipitation from storms. 

In tandem, changing weather patterns resulting from climate change mean that during the wet season from October to April the state can face intense storms that release large volumes of precipitation in short periods of time. Effective stormwater management is therefore critical to protect and serve homes, businesses and infrastructure in LA County.

 

Stormwater management objectives in LA County

LA County’s flood protection and water conservation system is one of the largest in the world, with a complex and extensive network of surface and sub-surface water management assets that collect, store, convey and infiltrate rainwater to mitigate flooding and maximize the use of stormwater as a resource—while also minimizing the impact of stormwater pollution on the environment. 

In prioritizing both flood control and water conservation, the County is taking a holistic view of water—in protecting its residents, its businesses and its infrastructure from the devastating impacts of flooding, it is simultaneously also turning that potentially destructive force into a resource that can be used to serve residents and replenish pressured water supplies. 

One stormwater best management practice (BMP) that meets both of these objectives is the drywell. In its most simple form, a drywell is a column drilled into the earth and typically filled with aggregate; collected surface water makes its way down the column and is infiltrated into the soil. 

Drywells have been used for stormwater management in the US since the 1930s, with Phoenix AZ an early adopter, and they are a useful tool in the civil engineers’ stormwater management toolbox. In its conventional form the drywell is a basic infiltration system, providing rudimentary stormwater management, but technological innovations have enabled the development of more effective and more efficient versions of the technology. 

 

The MaxWell® advanced deep infiltration drywell

MaxWell® is an advanced deep infiltration drywell system that collects and infiltrates surface water at depths of up to 120 ft.

Unlike conventional drywells, it incorporates a settling chamber (and optional additional pre-treatment chamber) that allows for sedimentation of total suspended solids (TSS), preventing clogging and extending the lifetime of the system out to beyond 50 years, and at just 4 ft in diameter it delivers exceptional deep infiltration for groundwater recharge in a compact footprint. 

To improve site safety and to ensure that the system meets site-specific requirements and regulations, design and installation are carried out by Oldcastle Infrastructure’s expert team. The team also provides inspection and maintenance services for drywells, ensuring that they continue to perform optimally for many decades.  

MaxWell was originally developed by Torrent Resources, which became part of Oldcastle Infrastructure in 2017. The team continues to deliver specialized deep infiltration design-build services as part of America’s leading water infrastructure solutions provider. 

 

How MaxWell is helping LA County

Developers and contractors have been working with Torrent Resources and Oldcastle Infrastructure for many years, installing around 1,400 MaxWell systems across LA County.  

Average annual rainfall in LA County is around 14.25 in, and MaxWell is designed to capture the 85th percentile of average annual runoff, which equates to 80% of average annual rainfall. 

With a drainage area of at least 43,500 sq ft for a single system, this means that MaxWell systems infiltrate around 433 million gallons, or 1,300 acre feet, of rainwater back into local groundwater supplies in LA County every year. 

In addition to providing a consistent groundwater recharge capability that helps LA County recharge its pressured aquifers, MaxWell also helps to protect citizens and businesses from flooding. 

In early February 2024, historic volumes of rain fell on Los Angeles for three days in a row, with nine inches falling over three days and total accumulations estimated to exceed 12 inches in some areas. The “atmospheric river” phenomenon caused hazardous conditions, with mudslides and debris flows resulting in extensive disruption and damage to the area. 

The County’s 1,400 MaxWell systems collected and infiltrated an estimated 250 million gallons of surface water during this three-day storm. This network of advanced deep infiltration drywells represents one component of a “sponge city” flood mitigation and stormwater harvesting capability that combines collection, storage, controlled release, conveyance and infiltration to reduce the impacts of storm events, capture stormwater for reuse, and return surface water to aquifers to replenish groundwater supplies. 

 

Learn more

MaxWell

Visit our MaxWell® product page to learn more about how MaxWell® can deliver cost-effective deep stormwater infiltration. 

Download the white paper to find out how Arizona is using groundwater recharge to combat flooding.

Online Design Tool

Design MaxWell® systems quickly and easily online with our Online Design Tool

 

References

https://www.drought.gov/states/california
https://www.usgs.gov/centers/california-water-science-center/science/geohydrologic-study-central-and-west-coast-basins
https://ourcountyla.lacounty.gov/strategies/strategy-9b
https://www.gov.ca.gov/2025/01/31/governor-newsom-issues-executive-order-to-help-california-capture-and-store-more-water-from-upcoming-severe-storms
https://pw.lacounty.gov/core-service-areas/water-resources/stormwater-management
https://wrrc.arizona.edu/dry-wells-for-stormwater-mgmt
https://www.weather.gov/lox/LAXRRMLOS
https://www.latimes.com/california/story/2024-02-11/l-a-staved-off-disaster-with-this-storm-extreme-weather-is-testing-our-luck
https://www.wired.com/story/los-angeles-just-proved-how-spongy-a-city-can-be

June 16, 2025

AI helps prevent major water main breaks

AI helps prevent major water main breaks

Preventing disruptive water main breaks

A large city in the South East used new AI leak detection technology to reveal 50 previously undetected leaks within its drinking water network, enabling repair crews to save over 167M gallons of non-revenue water and prevent costly and disruptive major water main breaks. 

 

The challenge

A major city in the South East was grappling with aging water supply infrastructure, with many of its thousands of miles of underground pipes more than 80 years old. These aging pipes are prone to leaks, which can result in major water main breaks that cause localized flooding that disrupts homes, businesses and essential services such as hospitals and law enforcement. 

Following two catastrophic and high-profile breaks, the city urgently needed a way to quickly and reliably identify and locate other potential developing leaks before they could erupt and cause further damage and disruption. 

 

The solution: CivilSense™ AI-driven leak detection 

City officials approached Oldcastle Infrastructure to use CivilSense™ AI-driven leak detection to support its burst mains response program, asking the team to deploy it rapidly across the 70 miles of its water distribution network that it considered to be of elevated break risk. 

The Oldcastle team deployed CivilSense™ in two phases, analyzing network GIS data to identify optimal locations for leak detection data sampling. Sensors were deployed across the network at a total of 223 accessible main line control valves and service curb stops.

In response to the city’s need for urgency, the Oldcastle team expedited data collection by opting for remote sensor data upload. 

The received data was analysed by the CivilSense™ AI, powered by FIDO Tech, to identify probable leak locations and rank them by volume of water lost. 

Each location was further investigated by our expert field team, who used correlation and top sounding techniques to pinpoint, locate and mark up all the significant leaks for repair by the city.

 

The outcome: reduced water main break risk

CivilSense™ successfully detected and located a total of 47 utility network leaks, along with a further three customer side leaks. These included two large main line leaks, one of which was close to a major road intersection in a busy area of the city. Each of these large leaks was estimated as losing 10 gallons of water a minute.

The city was able to use this data to carry out emergency repairs and to prioritize scheduled water infrastructure upgrade and repair work to address the higher-risk pipe sections first. 

Using AWWA nominal volumes, the total volume of non-revenue water being lost was calculated at 320 gallons per minute. This equates to around 460,000 gallons per day, or a total of almost 168,000,000 gallons every year. 

Each of these leaks represents a persistent risk of a water main break risk, so by addressing these leaks, the city helped to prevent the kinds of major main bursts that cause cost, damage and disruption to local people, businesses and essential services.

Download This Case Study

 

Learn more

June 13, 2025

New AI leak detection saves water utility $213,000

New AI leak detection saves water utility $213,000

AI leak detection technology saves money and gallons

A suburban Mid-West water utility used a new AI leak detection solution to locate a large water leak that had evaded traditional detection methods for years—saving $213,000 a year and preventing the loss of 350,000 gallons of non-revenue water every day.

 

The challenge

A major suburban city in the Mid-West was grappling with a non-revenue water loss challenge. 

Utility managers knew that there was a major leak somewhere in the system, but traditional leak detection methods had failed to locate it. Water was leaking from a storm drain, but there was no indication of a leak nearby; despite extensive efforts, the source of the leak itself evaded detection. 

Having tried three different leak detection techniques and technologies without success, after two years the utility decided that a better approach was needed. 

 

The solution: CivilSense™ AI leak detection

The utility partnered with Oldcastle Infrastructure and opted to use CivilSense™ AI leak detection to pinpoint the location of the leak.  

Having assessed the situation and identified the section of network where the leak was likely to be located, Oldcastle’s expert team deployed acoustic sensors at strategic points throughout the network section. 

These sensors gathered acoustic data that was then fed into a proprietary AI for analysis. The AI, powered by FIDO Tech, compared the data to its curated library of over 2.3 million acoustic signatures and confirmed the presence of a large leak in the network. 

Oldcastle experts then deployed two sensors on the section of pipe confirmed to have the leak, and used a technique known as “correlation” to pinpoint the precise location of the leak. 

 

About Correlation

Two sensors take perfectly synchronized data samples that are uploaded to the cloud, where a mathematical formula is used to calculate the precise location of the leak between the two sensors. 

Correlation is accurate to ±1½ ft, even under challenging conditions, which utilities confirm is a sufficient level of accuracy to locate a leak. 

This is equivalent to the accuracy of some alternative techniques, but has the benefit of being significantly less labor-intensive and faster and easier to achieve.

The outcome: $213,000 and 350,000 gallons saved

CivilSense™ AI leak detection successfully identified and helped pinpoint the exact location of the leak, which was a complete circumferential 1/16 inch wide break on a 6-inch metallic water main. 

The break was close to a gravel backfill trench around the homeowner’s storm drain, which meant that the water was able to quickly track away from the site of the break, infiltrate the drain and travel to a downstream connection to the city’s main storm drain, where it became detectable at a manhole some 334 feet away. 

At a water pressure of 60 psi, this break represented a significant water loss of almost 243 gallons every minute, or nearly 350,000 gallons per day. Based on the water utility’s local water production costs, this meant that it was costing the municipality up to $213,043 every year.

This costly and unsustainable water loss situation had baffled utility owners and stumped traditional detection methods for two years. Only CivilSense™ was able to detect and locate the leak quickly, reliably and accurately. 

Download this Case Study

 

Learn more

May 27, 2025

Cinco Ranch Custom Stormwater Management

Cinco Ranch Custom Stormwater Management

Custom Stormwater Management Solution

A new residential development in Richmond, Texas benefited from a custom stormwater management solution that expertly combined storage and treatment to mitigate flooding and manage water quality.

 

The challenge

During its design phase the engineers working on the Cinco Ranch residential development in Richmond, Texas faced a significant stormwater management challenge.

Nearby buildings and parking lots presented a number of impervious surfaces, meaning that the site would have to incorporate effective flood mitigation measures.

Limited space and a high local cost of land meant that a retention pond would either take over half the area of the parking lot, or be cost-prohibitive. Additionally, the geography of the local area allowed for only shallow construction. A pond could not be the solution. 

 

The solution

The specifying engineer worked with one of Oldcastle Infrastructure’s stormwater management experts to address site constraints, taking into account the impervious nature of the site and shallow outfall. The team decided on underground storage to maximize the use of land. 

Oldcastle Infrastructure worked with the engineer to design a site-specific custom stormwater detention and treatment system, combining the Nutrient Separating Baffle Box® (NSBB®) and StormCapture® technologies. The team used the Online Design Tool to collaborate and develop stormwater management designs quickly and easily. 

The NSBB was used for trash capture and pretreatment upstream of the underground detention, while StormCapture solved site constraints and prevented the need for a large, costly retention pond.

In addition to providing design support, Oldcastle Infrastructure representatives were on site during the installation. By providing  ongoing support to the contractor, installation was completed safely and efficiently.

 

About NSBB

The NSBB removes trash, sediment, Total Suspended Solids (TSS), and nutrients. The triple-chamber design removes high levels of TSS over a wide range of particle sizes. In addition, patented deflectors ensure no sediment scouring occurs during high flows, allowing for on-line installation without the need for separate diversion structures.

 

About StormCapture

The StormCapture system provides tailored, efficient storage that replenishes aquifers, manages stormwater, and ensures compliance with environmental regulations—helping projects like Cinco Ranch contribute to long-term water security and environmental stewardship. 

 

Benefits

Flexible to Design, Easy to Install

Unlike traditional stormwater treatment methods such as sedimentation ponds, the NSBB is smaller, more flexible and easier to install. Its shallow, small footprint is designed for easier and numerous placements

Designed for Easy Maintenance

The NSBB uses a patented screen system to capture and store debris in a dry state to minimize nutrient leaching and allow for efficient maintenance.

Increased Detention Capacity

StormCapture facilitated the addition of detention capacity without compromising the parking lot size, optimizing the use of available space.

 

Next

Carmel Village CMP Alternative

Carmel Village CMP Alternative

New Linear StormCapture® Configuration

After a collapsed corrugated metal pipe caused a sinkhole in a Chandler, AZ parking lot, a new linear StormCapture® configuration delivered a high-performance alternative stormwater storage solution. 

 

The challenge

Located in the heart of Chandler, Arizona—a rapidly growing suburb southeast of Phoenix—Carmel Village is a retail shopping center that serves both daily commuters and local residents. As part of a bustling commercial corridor, maintaining access and safety for vehicles is critical to supporting surrounding businesses.

However, a significant infrastructure failure created major disruption for over a year. A 96-inch corrugated metal pipe (CMP) storm drain beneath a primary driveway collapsed, resulting in a large sinkhole that made the shopping center’s parking lot and access route unusable.

This deterioration not only compromised safety and aesthetics, but also limited access for customers and deliveries, reducing the commercial viability of the property.

Further complicating the matter, the City of Chandler—citing long-term durability concerns—has banned the use of CMP in public infrastructure projects, favoring more robust, long-lasting alternatives.

While this particular project was privately funded, local contractor EKR Construction strongly advocated for a more permanent and high-performance solution that aligned with the city’s preferences.

 

The solution

To address the urgent infrastructure failure and ensure long-term performance, the project team selected Oldcastle Infrastructure’s StormCapture® system as the solution of choice. With its precast concrete, modular design, StormCapture offers high strength, long service life, and design flexibility that made it ideal for this application.

Given the layout constraints and the need to maximize storage in a confined footprint, the project utilized a linear StormCapture design, which allowed the system to fit seamlessly beneath the driveway while still meeting required stormwater storage volumes.

The StormCapture system not only addressed the immediate failure but also provided a sustainable stormwater management solution in line with Arizona’s stormwater challenges—where intense but infrequent rainfall events can cause flooding if not properly managed.

Oldcastle Infrastructure worked closely with EKR Construction during the planning and design phases to develop a layout tailored to the site’s specific volume and footprint requirements. The solution provided peace of mind to stakeholders by eliminating the risk of future collapse and offering a system that requires minimal long-term maintenance.

 

The outcome

The project was completed in March 2025, and the results were immediate and impactful. The parking lot was repaired and fully repaved, restoring both the appearance and functionality of the site.

Most importantly, the StormCapture system ensures long-term stormwater performance while enhancing structural integrity beneath the drive lane.

This project not only resolved a long-standing hazard, but it also demonstrated the viability and value of using StormCapture on private commercial developments. In a region like Chandler, this installation provides a model for resilient stormwater management that meets both immediate and long-term needs.

 

Learn more

May 19, 2025

The Lindon OW Building 2 CUDO Project

The Lindon OW Building 2 CUDO Project

Lightweight Modular Stormwater Storage

The first CUDO® installation in Utah helped a light industrial development in Lindon deliver high-efficiency lightweight stormwater storage. 

 

The Challenge

The Lindon OW Building 2 project in Lindon, Utah, marked a significant milestone as the first-ever installation of a CUDO® system in the state.

In collaboration with MKB Mechanical and with engineering support from Excel Engineering, Oldcastle Infrastructure needed to deliver a highly efficient, underground stormwater management system that maximized storage capacity while minimizing the system footprint.

 

The Solution

The modular CUDO® system was the ideal choice for the project, offering lightweight, high-strength components, a 95% storage efficiency, and seamless integration with site conditions.

While CUDO® is a proven solution, it was a new system to engineers and contractors in this part of the country, so the Oldcastle stormwater team provided on-site guidance and technical expertise to ensure a smooth and efficient design and installation process. 

Oldcastle’s stormwater experts collaborated closely with MKB Mechanical and Excel Engineering to optimize the assembly process, ensuring the system was installed efficiently and effectively.

 

Benefits of partnering with Oldcastle Infrastructure

  • On-site support Oldcastle provided hands-on guidance throughout to assist with assembling and positioning the CUDO® cubes, streamlining the installation process.
  • Adaptive installation approach The team worked closely with the contractor to adjust the system layout on site, demonstrating its flexibility and adaptability to various site conditions with a smaller footprint.
  • Collaborative, constructive teamwork The efficiency and success of the project was a testament to strong communication and problem-solving on the part of the Oldcastle team, contractors and engineers.

 

The Outcome

The CUDO® system was successfully installed over a four-day period, delivering an efficient and innovative lightweight stormwater storage solution.

The system provided 9,827 cubic feet of underground storage at 95% efficiency, exceeding the project’s requirements. Over 1,100 CUDO® units were used to achieve this.

 

Project highlights

  • Successful first CUDO® installation in Utah This project provided a reference for future implementations in the region, proving the effectiveness and ease of installation of the CUDO® system.
  • Positive contractor feedback MKB Mechanical shared valuable insights on the system’s assembly process and performance, reinforcing its potential for future projects.
  • Strong partnership and teamwork The collaboration between Oldcastle Infrastructure, the contractor, and engineers ensured that the installation proceeded efficiently and safely.

With CUDO® we were able to get the volume in without having to interfere with other existing utilities. A smaller footprint also means less digging and less gravel that goes in around the system. Specific to that job we didn’thave anywhere to stage dirt/ gravel so the less we needed was a big help. With the smaller footprint offsetting the labor of install it makes it a great option for a lotof applications.”

Benefits

  • Efficient stormwater storage The CUDO® system’s 95% storage efficiency minimized the system footprint while maximizing capacity.
  • Lightweight and easy to install The modular components made handling and assembly quick and straightforward, even for first-time users.
  • Long-term maintenance accessibility The large interior openings allow for easy inspection and maintenance, ensuring long-term system performance.

The Lindon OW Building 2 project showcased the efficiency, adaptability, and long-term viability of the CUDO® lightweight stormwater storage system. 

 

Next

December 18, 2024

Communications Broadband Deployment: Duralite® vs. Polymer Concrete

Kennedy Broadband, LLC is a full service outside plant construction contractor
that specializes in fiber optic outside plant deployments throughout the
southern and midwestern U.S. Their expertise encompasses consulting, project management, engineering and design, splicing, and FTTx.
This comparison study demonstrates the relative performance and benefits of
Duralite and polymer concrete enclosures Kennedy Broadband, LLC experienced during a recent installation.

CHALLENGE
Kennedy Broadband, LLC installed a Duralite and a polymer concrete enclosure as part of a communications broadband deployment project along Highway 17 outside of Richmond Hill, GA. This installation was part of their regular operation and each portion (Duralite and polymer concrete) included additional communications components, including an above-ground pedestal for polymer concrete and plastic conduits for fiber distribution for Duralite.

SOLUTION
Kennedy Broadband encountered distinct advantages of Duralite over polymer concrete from weight reductions and increased safety to time and cost savings.

“We found the Duralite enclosure to be a lot easier to handle. It took less people to do it. And if you don’t have an excavator, you don’t need one to set the Duralite,” said Bjorn Skogen from Kennedy Broadband.

Duralite enclosures were safer and easier to handle. “It gives us peace of mind as managers to be able to send two guys out without having to worry about back injuries or having polymer concrete vaults rolling off of a trailer and severely hurting them,” said Kennedy Broadband Operations Manager James Kennedy.

Maneuverability was another clear advantage of Duralite. It came as a pleasant surprise, according to James Kennedy. “I could easily move and set a 48-inch vault by myself. Anyone involved in underground communications construction knows this is a game-changer.”

This Kennedy Broadband deployment project proved Duralite to be a formidable and versatile enclosure product when compared to polymer concrete.

BENEFITS

Tier Rating
Duralite enclosures have the same tier 15 and tier 22-rated strength as polymer concrete, along with the same protection for underground communication and utility infrastructure—but with significantly less weight and easier maneuverability.

Lighter Weight
Duralite enclosures are up to 75% lighter than polymer concrete, making them easier to transport and install. It doesn’t require heavy machinery, such as an excavator to lower and position underground. Even if an excavator is used to dig the hole, that machine can be free after digging to excavate subsequent holes, so machinery and time are maximized.

Safety
Duralite can be carried by hand and doesn’t require a heavy machine to lower
underground. Polymer concrete presents safety risks, for example, if there’s loss of balance when guiding the product into the ground or stacking up enclosures for transport.

Cost Savings/Efficiency
Faster and safer installations save time and costs. Duralite installations take an
average of 30% less time than polymer concrete installations. Additionally, not having to rent or use heavy machinery saves on fuel costs.

Modifiability
Unlike polymer concrete, Duralite is engineered to allow contractors to make modifications at the installation site with common tools.

Sustainability
Duralite is more sustainable than polymer concrete from manufacturing through installation. Manufacturing is highly automated and uses up to 65% recycled materials. During installation, Duralite has a lower carbon footprint than polymer concrete, with fewer trips from the factory to the distribution stocking yard, and from the yard to the project site.

Plus, because it’s up to 75% lighter than polymer concrete, you can use more fuel-efficient trucks to transport it, and you won’t need heavy machinery to lift, lower, and position it underground.

_______________________________________________

August 28, 2024

Emergency Detour on Teton Pass

Emergency Detour on Teton Pass

In response to a catastrophic failure on the Teton Pass Highway due to a massive landslide, Oldcastle Infrastructure partnered with the WYDOT and Avail Valley Construction to construct an emergency detour in time for the 4th of July weekend.

This project aimed to restore connectivity between Idaho’s Teton Valley and Jackson, Wyoming, ensuring safe passage for commuters and tourists. The urgency of completing this project before the upcoming 4th of July holiday imposed significant time constraints

 

The challenge

The project presented several critical challenges. To begin with, a swift turnaround was essential, with the detour needing completion in under 15 days to minimize disruption and restore this vital transportation route.

Logistically, transporting 120-feet worth of box culvert from Oldcastle Infrastructure’s Nampa, Idaho, plant to the project site required meticulous planning and coordination due to the distance and logistical constraints.

 

The solution

Oldcastle Infrastructure responded to these challenges with decisive action. Our engineers quickly produced and obtained approval for CAD drawings to expedite the manufacturing processes, and we promptly cast 19 box culverts, meeting project specifications and timelines.

Collaboratively, Oldcastle Infrastructure partnered with other CRH companies and the Wyoming Department of Transportation (WYDOT) to seamlessly integrate the box culvert into the detour construction, ensuring efficient project execution and compliance with safety standards.

 

Benefits

The completion of the emergency detour yielded several key benefits:

Timely Restoration:
The detour opened successfully before the 4th of July weekend, enabling uninterrupted travel for over 15,000 daily commuters and tourists.

Enhanced Safety:
The new detour, featuring a bidirectional roadway with concrete barriers, ensures safer passage.

Community Impact:
Oldcastle Infrastructure demonstrated a commitment to supporting local communities in times of crisis.

Shorter Onsite Construction Time:
Oldcastle Infrastructure’s efficient processes reduced onsite construction time, minimizing disruption to traffic and local businesses.

Resilience:
The robust design of the detour ensures long-term durability against natural elements, providing a reliable transportation route for years to come.

Oldcastle Infrastructure’s rapid and collaborative efforts with WYDOT and a “One CRH” approach exemplify effective crisis management and community service.

By swiftly addressing the challenges posed by the Teton Pass landslide, Oldcastle Infrastructure not only helped restore a critical transportation link but also ensured the safety and convenience of thousands of commuters and tourists.

_______________________________________________

|  Featured Products
Box Culverts

 

Download Full Case Study

August 20, 2024

Toyota of Lewisville, Texas | StormCapture

Toyota of Lewisville, Texas | StormCapture

Stormwater Detention Overcomes Time Constraints and Limited Space

By selecting StormCapture®, a Texas car dealership not only achieved essential stormwater detention but was also able to expand its available parking capacity.

 

The Challenge

Toyota’s new car dealership in Lewisville, Texas, presented both exciting opportunities and unique challenges.

Working with the specifying engineer, the Oldcastle stormwater team quickly realized that this site posed constraints regarding the amount of space available, and the clock was ticking to find a solution with delivery timing at the forefront.

The site constraints and the urgency of delivery timing added an extra layer of complexity to the installation, shipping, and delivery of the units.

However, the team adopted a collaborative approach and used these challenges to prompt the adoption of creative solutions.

 

The Solution

Oldcastle recommended a StormCapture® underground stormwater detention system to provide high-volume storage and infiltration.

The modular precast system not only met project requirements, but in providing a solution to deliver some 75,000 cu ft of detention capacity it also enabled the dealership to expand the size of its parking lot.

The decision to incorporate StormCapture into the design was driven by its quality and reliability, and its ability to meet the dealership’s requirements while also delivering the unexpected additional benefit of greater parking capacity.

StormCapture’s precast modular design meant that the installation process was straightforward and efficient. The installation process took 45 days, and was completed with one crane, accommodating both limited space and tight project timelines.

 

Benefits

INCREASED DETENTION CAPACITY

StormCapture facilitated the addition of detention capacity without compromising the size of the parking lot, optimizing the use of available space.

ON-TIME DELIVERY

Despite the challenges in logistics, the project maintained an average of 10 trucks per day, ensuring timely delivery that adhered to the contractor’s timeline.

PRECAST CONCRETE DETENTION SYSTEM

Comprising some 86 4½ ft StormCapture modules with 50 link slabs and 50 grade slabs, StormCapture’s modular precast concrete design showcased its suitability for the project and contributed to its success.

 

Next

Nevada and Commonwealth Apartments | MaxCapture®

Nevada and Commonwealth Apartments | MaxCapture®

The Nevada Street and Commonwealth Avenue Apartments in Chandler, Arizona are newly constructed multifamily apartments that needed a solution to address both stormwater detention and deep infiltration.

With our full solutions approach to stormwater management, Oldcastle Infrastructure looked to modernize this community with the use of the brand new MaxCapture®, combining Oldcastle Infrastructure’s StormCapture detention modules and MaxWell® drywell solutions into a single system, all while saving the owner and contractor time, costs, and land space.

CHALLENGE

Addressing the need for both detention and deep infiltration, while cutting down on the costs, installation time, and land usage that is typically required. Generally, two separate products from two separate companies are needed, if detention and deep infiltration are both required on a site. Solving both issues with a single product, one that had never been installed before, required a comprehensive approach ensuring this groundbreaking project ran smoothly and set the precedent for future projects.

This implementation project required the coordination of all parties involved so Torrent, Oldcastle Infrastructure, and the contractors could work seamlessly together. With nearly 50,000 ft3 of storage volume installed, it was also necessary for the city of Chandler to approve the use of the drywells.

SOLUTION

This project showcased Oldcastle Infrastructure’s turnkey solutions by leveraging the first-ever installation of MaxCapture, an innovative, one-of-a-kind combined detention and drywell system. While detention and drywell system installation is typically costly, labor-intensive, time consuming, and usually requires a very involved design process, Oldcastle Infrastructure’s ability to create comprehensive solutions that address core needs alleviated those hurdles.

BENEFITS

Land Allocation
Utilizing MaxCapture allows for land space to be saved and allocated for other revenue-generating purposes thanks to its stacked design.

Cost Efficiencies
Since MaxCapture is self-contained, the design and installation process required less excavation and fewer materials than a traditional two-product system.

Accelerated Timeline
Oldcastle Infrastructure’s engineering and design resources, streamlined the design process for specifying engineers.

_______________________________________________

PERKFILTER® OFFERS HALLMARK SOLUTION FOR HALL CREEK ENHANCEMENT PROJECT

Salisbury, MD

Up the creek. Without funding or a plan, that’s where a consortium of civic, corporate and volunteer entities found themselves back in 2009 when faced with a rather large clean-up effort of Hall Creek in Beaverton, Oregon.

Undeterred, the city of Beaverton started the process by applying for a capital grant with Metro, the agency that oversees the Portland metropolitan area. Created more than 30 years ago, Metro coordinates regional planning for managing growth, infrastructure and development, often crossing various jurisdictional boundaries while serving an area of some 1.5 million residents.

Beaverton, a community of some 92,000 people, is located about seven miles west of downtown Portland, Oregon. “We wanted to clean up an area of Hall Creek that had become known as the dirtiest section of the creek,” said Debbie Martisak, Project Manager in the Public Works Department in the city of Beaverton. “It was because of the big car lots and mechanics shops that are there,” she added.

In 2012, the city was awarded a significant grant from Metro in the amount of $354,000 to help fund a 650-foot section of Hall Creek. Officially known as the Hall Creek Water Quality & Pathway Enhancement Project, the plan was quite ambitious.

According to the Beaverton Public Information office, the goal was to “realign the creek and adjacent trail, reconnect the floodplain, remove invasive plants, stabilize banks with native plants, remove impervious surfaces and create swales for enhanced water quality.” Martisak noted that the Metro grant amounted to about one-third of the total estimated cost of the project. “This grant really sparked the design and made it possible to have this project happen,” she said. “Without that money, we wouldn’t have been able to afford it. So, with the grant in hand, we went through the design process.

MEDIA FILTRATION

“Putting a filter vault in wasn’t part of the original plan, but the design process indicated that this was the right step to take for our area,” Martisak said. “It became important to us once we went through the design process and began looking at hydrology, pervious and impervious surfaces, and what’s actually flowing into the creek to be treated by this vault.

“It’s a very substantial area, an area that’s highly industrial and commercial. It’s in the heart of what we call our downtown. So, we started talking to our agency called Clean Water Services about our plans, and what types of things that they would like to see. They’re a regulatory agency here in Beaverton that provides permits for this area of Washington County.

“They were also a big supporter of our plans, donating plants and their employees’ time. They recommended having a filter vault in this location, to collect all of the runoff on private property and a little bit of public property as well.

“Most of what we were doing was to improve the urbanized area, taking what was a poorly functioning creek and make modifications to the creek that would support the aquatic life and hydrology of the area. It’s a straight and narrow creek, with high velocities that was scouring out the banks by up to four feet. We had to do something.

“There’s quite a bit of area there that was not being filtered, and it was a very dirty area of the city because of the types of businesses that are there. So, we decided to add on a filter vault to our project.”

Martisak learned, however, that at that time there was currently only one approved supplier for these vaults. “So initially, we were only getting one bid, which isn’t the way that we do business. It’s not normally cost effective, especially when we’re talking about a $40,000 to $50,000 piece of equipment for our infrastructure.

“Therefore, we requested that they work out and approve another manufacturer and different design. This resulted in Oldcastle® Infrastructure getting their PerkFilter® vault approved in addition to a third manufacturer as well, so now there are more competitors in the area.”

Deon Lourens, Area Technical Manager with Oldcastle Infrastructure, explained that there are several advantages to the PerkFilter system. “Its cartridges have no moving parts and no cartridge hood, allowing for easier maintenance observation. In addition, its design allows for fewer cartridges than alternative models, and the bypass flow underneath the cartridge bay limits re-entrainment of pollutants.”

He noted that cartridge lifecycle can range up to three years, depending on the pollutant load. “The cleaner the influent,” he said, “the longer the duration between maintenance cycles.”

OLDCASTLE INFRASTRUCTURE’S STORMWATER

Martisak described the city of Beaverton’s relationship with Oldcastle. “We ended up hiring Oldcastle. They came in as the lowest bidder, and they came up with a design for us, together with our engineer who sat in with Cardno WRG, the engineering firm who did the design work. They approved our shop drawings and they made modifications as they saw fit, in consultation with Oldcastle.

“Oldcastle and Cardno WRG were very helpful in discussing exactly which area is being covered by the vault, how much water is being filtered, and the precise numbers for this creek enhancement project.”

Construction finally began in July 2015. “That’s when our contractor started excavation,” explained Martisak. “We’ve been working on it since, and our own city staff actually installed this vault. So, it was a cost saving to the city to purchase the vault, and our team of engineers worked with Oldcastle to see what we were going to get before it came onsite, to work with them regarding how it was going to be delivered, and how it was going to be set up.

“They were onsite with us when it came, and it was crucial to make sure that it was set up with the correct grade and level. Our city team could place and install the connections and everything that comes into this vault, as well as the pipes that come out of the vault.

“That saved us quite a bit of money, since our labor hours are much less than if we would have contracted it out to another contractor. That was a unique aspect to this project, having our city staff able to place and install the vault. This was a challenge that we overcame, and it came out perfect.”

Another issue the city encountered before the work could get very far along was a problem with what was found underground where the vault was to be placed.

“We ran into a situation with some contaminated soil,” explained Martisak. “When we were digging, we found oil sheens. We would dig a hole, and it would just fill up and have a sheen to it. We had it tested, and we had to reclaim everything that came out of that area, and send it to a specific location to be handled quickly.

“We’re talking very low amounts here. We did more than we had to, but when we found something in one small spot, we decided to treat the whole area. These oils we found are likely a direct result of the businesses that have been in that area for decades.” The oil contaminants weren’t the only underground problem. “When we started digging our test holes for this new vault, we found that some major electrical lines were in the way, so we had to move the location of the vault, in order not to have to go under or above the electrical transformers. You never know what’s underground until you start tunneling in.

“So, we had to do some adjustments with moving the vault’s alignment. The original design had one way for the pipes to go in, but now it’s turned and moved over so we can get a more direct shot without having to worry about a transformer.”

LOW-IMPACT DEVELOPMENT

The PerkFilter vault was just one element of this overall water quality improvement effort. In addition, the city installed new curbs, a landscaping planter and did some parking lot resurfacing. In the project area, they now have some pervious concrete, several plantings and a new boardwalk.

The plantings were part of a low-impact development effort. Martisak indicated that native plants, shrubs and trees have been newly planted along both sides of the creek. Local volunteers assisted in the plantings, conducted in October and November of 2015, and in January 2016. A final volunteer planting day took place in April 2016 on Arbor Day, in conjunction with a ribbon cutting ceremony for the new trail that was created in the area.

“This helps ensure that the area is going to eventually maintain its own water quality, as the planted trees get bigger, the shading of the creek increases, and as the stormwater is being treated by plants that were specifically chosen for this environment,” Martisak said. “It’s a low-impact development project.”

The Oldcastle PerkFilter vault is now in place, and is filtering the water and taking out the garbage that is collected from the storm system, including the runoff from the parking lot, before it goes directly into Hall Creek.

“The vault was operational through all the big winter storm events that we had,” Martisak said. “Beaverton has gone through some record storms, and it has performed really well.”

She explained some of the other elements in the local enhancement effort. “We already had plantings and water quality plants that went into this project. We also did mitigation upstream, to ensure that we’ve got good shading of the creek. We pretty much took out most the trees that were non native and invasive. When we cleared them all out, it left the area looking very bare, although it was nice to be able to see the aesthetics of what we were able to change in the channel.

“For water quality, we have a rain garden that is also part of the project. We have two swales that are part of this project, that are taking stormwater outfall from the parking lot at the car dealership. The filters we’re using are all from plants. We’ve also made changes to the creek’s alignment, to slow it down, and to give the channel and the area downstream a better chance to avoid flooding.

“The other stormwater work we have done is to install new catch basins in the parking lot for an apartment complex on the north side of the creek to handle the stormwater coming off these adjacent properties.” Additional details of the other stormwater aspects of the project were provided by Cedomir Jesic, an engineer with the consulting firm Cardno WRG. “There are two treatment trains. One is the filter vault, with catch basins clearing the stormwater of debris before it even reaches the vault. Then there is also a series of catch basins throughout the parking lot, with a water quality pretreatment manhole that lead into the swale.

“It wasn’t entirely clear what drains here, so with the catchment area it was assumed that it can either drain to this vault, or to the adjacent water quality swale. So, we have the vault, and we have a water quality planter, a swale, that treats another part of the catchment area.

“A part of the development drains directly to this water quality facility. So, on this project we are using both mechanical treatment, with the PerkFilter, and we’re also using vegetative treatment with the water quality swale.

“We were very fortunate that we were able to build this vegetative facility and call it a conveyance facility, but it’s planted as a water quality facility, so we know that some treatment will occur. This is with the swale.

“We’re doing as much water quality treatment as is feasible, with existing outfalls. There has been extensive landscaping. So, there has been stream restoration, enhancement and improvement of water quality.”

One of the problems that had been encountered prior to the start of this project was that there are five separate private property owners in this area of Hall Creek. As Martisak commented, it had become a case of “who’s doing what?”, with the result being nothing.

“There was a trail,” she said, “but it was a bit dicey, because it wasn’t maintained by these property owners. So, we took over responsibility not just for the installation of this filter vault on private property, but we will be continuing to do all the maintenance on it forever, changing all the filters forever. We will also be ensuring that these plants are maintained and nourished for three years. We did everything we possibly could to make this a very natural, established end product. We went the extra mile to get this filter vault. We had to get more money to do the right thing.

“That shows the city’s sense of responsibility for the creek and its integrity by actually paying some $40,000 for a piece of equipment that wasn’t initially planned. We didn’t have to do this, we weren’t required to; it was a matter of doing the right thing, and that’s what the city did. We were able to take all the issues that we saw, and make something that is not just effective, but is beautiful. The project turned out incredibly fabulous.”

Cardno WRG’s Jesic was equally impressed with the finished project. “The city crews did a really good job,” he said. “There were different groups working within the city – there were utility and pipe crews doing one thing, street crews doing another thing, and the landscape people working with volunteers to do all the planting.”

Martisak noted that without the Metro funding, this project might never have taken place, or would have been significantly scaled down. But the city of Beaverton didn’t sit idly by, waiting for a funding decision. They were incredibly pro-active.

“We got 26 big local supporters for this project – big players who came to the table and said at the beginning of the process that they like the idea, that there is a strong need here, and that they support this project.

“Because we had so many supporters that came to the Metro meetings, I think the grant committee was overwhelmed with the fact that there was so much support, it would have been difficult for them to say ‘no.’ But without that grant, I don’t think this project would have gone forward to the level that it did. We probably would have had to do a low maintenance project and just cleaned it up a bit.”

Download Full Case Study

THE STAKKABOX ULTIMA CONNECT CHAMBER – COMMUTER RAIL

The STAKKABOX Ultima Connect Chamber provided a transportation authority with an outstanding combination of durability, customization, and ease of installation for protecting sensitive railway components.

THE CHALLENGE

Commuter rail lines in densely populated areas rely on intricate communications and signaling systems for efficient and safe operations. The
infrastructure that protects those systems must be durable, reliable, and easy to configure for ongoing upgrades.

The transportation authority was in search of an alternative to the existing polymer concrete vaults to support the need to add capacity to the system (including additional fiber cables) in the Philadelphia area. Typically, polymer concrete boxes are used along with cable trench and conduit to protect transit signal and communications wiring.

The standard polymer concrete boxes are difficult to modify without compromising strength, especially when a large number of conduits must interface in a single box. The transit authority needed a solution that could accommodate a higher quantity of 6″ holes (cored-out conduit access holes or square cut-outs in the field) while maintaining the structural integrity of the chamber.

THE SOLUTION

Oldcastle Infrastructure provided one 4′ x 4′ x 4’ STAKKABOX Ultima Connect Chamber with Steel Frame and H20 Composite Covers, configured so the conduit-to-vault transition holes could be drilled on site.

Installation was simple and straightforward:

| An excavator was used to dig a hole in the ground.

| The excavator then lifted and set half of the body (a total of 5 rings), followed by the balance (an additional 3 rings) to create an entirely assembled chamber.
(Note: This configuration could also be built directly in the hole, one ring/layer at a time).

| Holes were cored out on opposite sides of the box (15 on one side, 8 on the other) and conduit access extensions were inserted.

| The area around the chamber was backfilled.

| The frame was placed on the body, and composite covers were secured to the frame with screws.

Total time for installation was approximately 3 hours.

“Everyone was extremely impressed with the ease of installation and accessing the conduit through the body.”
Cort MacLean | Transit Account Manager

BENEFITS

THE STAKKABOX PROVED TO BE AN OUTSTANDING SOLUTION FOR THE TRANSIT AUTHORITY’S REQUIREMENTS:

| Openings for cable trench or conduit can be pre-fabricated or cut on site without compromising the chamber’s strength and performance.

| Rings can be added or removed to reach a customized final depth as dictated by the site conditions, due to the Ultima’s innovative layered design.

| The Glass Reinforced Polyester Resin (GRP) components offer more durability and will not crack when placed close to vibrating rails.

| The body components and covers are lightweight, making it safer for the personnel installing the cables and providing easier access to the cables in the future.

GOLD STANDARD DURABILITY: THE “TRACK TEST”

After all tests, the STAKKABOX Ultima Connect Chamber met all form and function requirements. In fact, no sidewall flexure was observed in the chamber even with 15+ six-inch diameter holes cut on one side for conduit access. The box was left in the transportation authority’s main maintenance way next to the rail and will undergo a performance review for a period of 3-6 months. The installation crew was extremely impressed with the ease of installing the box and accessing the conduit through the body. A second unit (STAKKABOX Ultima Connect Chamber) is scheduled to be installed within the next few months.

www.OldcastleInfrastructure.com

Download Full Case Study

Lake Elsinore, California BioPod™ Installation

Lake Elsinore, California BioPod™ Installation

Custom Green Infrastructure Solution

A custom BioPod™ green infrastructure solution enabled contractors to meet stormwater treatment requirements with fewer systems as part of a new superstore construction project in Lake Elsinore, California.

 

The Challenge

General contractor Apple Valley Construction needed to install a sustainable stormwater treatment solution for a new Walmart commercial development in Southern California.

However, site and budget conditions meant that the technology that had originally been proposed would be too expensive and would have insufficient design flexibility to accommodate site conditions.

The contractor needed an alternative large-scale solution with flexible design that met site-specific needs.

 

The Solution

The Oldcastle Infrastructure stormwater team worked with specifying engineers Kimley-Horn to develop a solution that would reduce cost and complexity while preserving performance.

Oldcastle experts engineered a custom solution comprising three larger BioPod biofiltration systems. The three systems are the largest individual units designed and installed in Southern California to date, and provide stormwater treatment equivalent to the originally specified technology but in significantly fewer units.

 

The Outcome

By collaborating with Kimley-Horn early in the design phase, Oldcastle’s stormwater experts were able to develop a custom solution that delivered high performance, site-specific stormwater treatment in a cost-effective package.

Even when incorporating larger individual units, BioPod’s overall compact footprint enabled the contractor to use a smaller number of units to consolidate the green infrastructure system into one area, while accommodating both the treatment flow rate of 0.86 cfs and the peak flow rate of 20 cfs.

 

Benefits

QUICK TO INSTALL

| BioPod was quick, easy and safe to install for Apple Valley Construction. Using BioPod in place of the alternative technology allowed for all three units to be installed in just 13 hours, saving the contractor a significant amount of labor time.

FLEXIBLE DESIGN

| Despite site challenges and budgetary restrictions, BioPod was able to meet site-specific requirements for size, reducing the amount of materials and units needed for installation while maintaining an aesthetically pleasing design for the end user.

SUSTAINABLE SOLUTION

| Fitting seamlessly into standard site drainage, BioPod built long-lasting green infrastructure into this Walmart site. Not only do the BioPod units result in a more efficient installation process for the crew, but they also incorporate an advanced biofiltration design for an environmentally friendly stormwater solution.

“In the face of a challenging site, the Oldcastle team designed an exceptionally large custom stormwater treatment system that will provide the performance and reliability required for many years to come.”

Britt Sweet

Oldcastle Infrastructure

Project details

Owner: Walmart

Contractor: Apple Valley Construction

Consulting Engineer: Kimley-Horn

Solution: Three 11′ x 26′ x 8′ BioPod systems

 

Next

X

Looking for a quote for your project?
While browsing our products, select “Add to Quote Generator” to quickly get an estimate for everything you need.